JNR LTD was tasked with installing glass rock steel protection and ablative batt to the hospitality lounge at Stoke City Football Club.

 

Planning

A risk assessment and method statement was put into place before any work was carried out; a
SSSTS supervisor was stationed on site in order to oversee operatives. A fire protection system was
planned and put into place with the main client (Scotts). A system was also put into place to ensure
all materials were stored correctly and any waste or unwanted materials were correctly disposed of.
All working operatives were DBS checked before any work was carried out as well as all operatives
having a CSCS card and being FIRAS trained.

Objectives

  • ┬áDiscussion and effective communication with Client to Assess and plan implementation of materials and other required work.

  • Preparation of building site and distribution of materials across the site

  • Implementation of work.

  • On going communication with work force and client to ensure all parties are aware of proceedings throughout the period of work.

  • Closing down discussion with Client once work is completed.

Execution

  • Identify key areas of work and client requirements.

  • Establish required number of workforce and quantity of materials.

  • Ensure all work is carried out according to regulation guidelines and company policies.

  • Overcome and rectify any potential barriers or problematic issues.

  • Advise client once work is completed, convey any problems that may have arisen and discuss payment protocols.

Results

  • Completed and integrated fire protection system to meet accreditation requirements.

  • Satisfied client.

  • Successfully received payment.